Ungogo Community Electrification

Phase 1 grid extension to 5 communities in Ungogo LGA....

Project Overview

Phase 1 grid extension to 5 communities in Ungogo LGA.

Project Milestones

Site Survey and Pole Mapping Completed

Complete survey of the 5 communities.

Due: April 2024

Procurement of Materials In Progress

Poles, conductors, and insulators delivered to site.

Due: June 2024

Pole Erection Pending

Erection of all high-tension and low-tension poles.

Due: September 2024

Project Information

  • Project Code: REB/PROJ/2024/001
  • LGA: Ungogo
  • Status: Ongoing
  • Start Date: March 1, 2024
  • Expected Completion: December 31, 2024
  • Project Manager: Hajia Aisha Bako
  • Contractor: PowerGrid Solutions Ltd.