Dala Solar Mini-Grid Pilot

Installation of a 150kW solar mini-grid to power the Dala industrial cluster....

Project Overview

Installation of a 150kW solar mini-grid to power the Dala industrial cluster.

Project Milestones

Environmental Impact Assessment (EIA) Pending

Submission and approval of EIA report.

Due: September 2024

Project Information

  • Project Code: REB/PROJ/2024/002
  • LGA: Dala
  • Status: Planning
  • Start Date: July 15, 2024
  • Expected Completion: June 30, 2025
  • Project Manager: Dr. Salisu Danbatta
  • Contractor: SolarWave Energy NG